docs(migration): reconcile the plan with the E0 issues and merged work - #15252
Conversation
|
➖ v2 migration progress: 0.9% → 0.9% (0 done, 0 total, 0 dropped; 86/9829 cells) Placement: 0 new marked lines in shared files, 0 new Ratchets: 9 core-internal imports (base 9); shared patches by rung 29 seam, 1 patch (base 29 seam, 1 patch). No change to the progress map. |
Code Review SummaryStatus: No Issues Found | Recommendation: Merge Files Reviewed (3 files)
The E0 issue mapping matches Part B, the remaining-unit count is 70, and the referenced merges (#15231, #15232, #15238, #15246, #15248) and the 9 core-internal import ratchet are consistent with Reviewed by deepseek-v4.1-flash-1017 · Input: 67.1K · Output: 9.9K · Cached: 983.8K Review guidance: REVIEW.md from base branch |
Coordinator reconciliation micro-PR. Fixes plan self-consistency findings; no status cell, unit, gate or decision changes (status cells are in #15251, which touches other lines).
newplus U-E1-05 beyond #15108)migration-context.mdstatusv2-host-strategy.md§4v2-host-strategy.md§6 rule 24c51aab(placement.ts --imports): agents plugin addspermission,shell,tool-output,util/wildcard; config discovery addslocationNot in this PR: the #13750 body still points at
kilo-v2(user update); the[v2-port]issue batch is not mapped (needs a decision); the rung labels of the #15018 config lines (open question to the user).Checks:
bun script/upstream/progress.ts --checkup to date. No Changeset.